Well, you paid him all, so what is done is done. You are likely not to hear from him again. You can try taking him to court.
But why did you pay the full amount? It is common practice to withhold payment until practical completion (habitable), and a further and final payment after a defects period has expired - generally 6 months. So until it is habitable you should be holding at least 30% at a bare minimum of the contract value. To not do so is asking for trouble.